Fibre optic installation offshore Norway

Global Maritime contracted Aquatic for support with the installation of a Fibre Optic Cable offshore Norway, for their end client Equinor on the Njord FOC Installation project.

Aquatic led and delivered a collaborative scope of services which also included fellow Acteon company InterMoor UK.

All was completed within schedule and without any incident.

Project
Njord FOC Installation 

Product
The 40km long fibre optic cable was delivered on an 8.5m industry standard ‘Co-Flexip’ drive reel, gross weight with product 107Te.

Vessel
Olympic Challenger

Location
Norwegian North Sea

Mobilisation
Kristiansund

Services Delivered
Aquatic delivered the following equipment
  • AQPR-08-150Te Powered Reel Drive System
  • AQTT-8-3Te and AQTT-07-5Te Two Track Tensioner Systems
  • AQSC-3m Over-boarding Chute

Personnel
  • 2 x Aquatic Supervisors – from mobilisation through offshore phase to demobilisation
  • 4 x Aquatic Technicians – from mobilisation through offshore phase to demobilisation
  • 2 x InterMoor Naval Architects – Support at mobilisation